Works on Bujanovac-Bukarevac railway completed – RZD International reconstructs first of three southern Corridor 10 sections
Source: Tanjug
Friday, 02.12.2016.
11:56
Comments
(Photo: Ivana Vuksa)
The superstructure and the substructure of the railway have been completely replaced, five switch points have been installed, 13 railroad crossings have been reconstructed, as well as two stations and low platforms. The contact network has also been renewed. As a result of the reconstruction, the speed of trains has increased to 120 km/h, the report specifies.
The model of performing construction and mounting works in the 36-hour shutdown regime was applied in Serbia for the first time, removing the need for a total shutdown of rail traffic. Furthermore, during the peak period, from mid-June till late August, train traffic carried on uninterrupted.
RZD International continues reconstructing the Vinarci-Djordjevo section, and the plan is for the works on the Vranjska Banja-Ristovac to be completed soon.
The cost of building and modernizing the three southern Corridor 10 sections amounts to more than USD 38 million and is being realized through a Russian state loan.
Tags:
RZD International
railway reconstruction
Bujanovac Bukarevac railway
Vinarci Djordjevo railway
Vranjska Banja Ristovac railway
Corridor 10
switch points
railway crossings
contact network
Comments
Your comment
Most Important News
Full information is available only to commercial users-subscribers and it is necessary to log in.
Follow the news, tenders, grants, legal regulations and reports on our portal.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno,
uz konsultacije sa našim ekspertima.