Final section on Corridor 10 to be completed by end-October
Comments
(Photo: eKapija/S.M.)
The most demanding part of the job is the construction of a gallery for the purpose of a permanent stabilization of the C6 slope at the entrance to the Bancarevo tunnel in the left traffic lane. The company Integral Inzenjering is already building the gallery, which will be located above the left lane in the length of 160 meters.
– The asphalting works on the left lane and the equipping of the section with traffic signalization are in progress. The equipment of the Bancarevo tunnel with the electro-mechanical equipment is also in progress. The works on the stabilization of another two slopes are also ongoing – the PE Corridors of Serbia says.
The section features five bridges of the total length of 297.3 meters, 27 slopes and the 733-m Bancarevo tunnel.
Tags:
Corridors of Serbia
Integral inženjering
Corridor 10
Corridor 10 eastern leg
Bancarevo
Crvena Reka
Prosek
construction of a gallery
stabilization of C6 slope
Bancarevo tunnel
asphalting
traffic signalization
electromechanical equipment
bridges
Comments
Your comment
Most Important News
Full information is available only to commercial users-subscribers and it is necessary to log in.
Follow the news, tenders, grants, legal regulations and reports on our portal.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno,
uz konsultacije sa našim ekspertima.