Zijin to expand copper processing capacity in Bor – Reconstruction of foundry and construction of new electrolysis and sulfuric acid facilities
Source: eKapija
Sunday, 01.03.2020.
11:59
Comments
Illustration (Photo: Zhao jian kang/shutterstock)
Parts of the facility will be designed to immediately meet the capacity of 200,000 tons a year, whereas, in other parts of the facility, enough room will be left for an expansion of the capacity in the future. In addition to increasing the capacity of the production of the foundry, the reconstruction will also involve the upgrade of the obsolete equipment and the degree of environmental protection.
As said, the plan is to reconstruct all the production and side facilities, from the transport of the copper concentrate to the processing facility to the production of cathode copper.
According to the general project plan, the project is split into the system of preparation of raw materials, foundry system, electrolysis system, system of production of acid from waste gases, slag flotation, service systems and transport and information systems.
The plan also includes the reconstruction of the facility for batch preparation, the construction of a new system for steam drying of a capacity of 82 tons per hour, which will be located to the south of the current one, the reconstruction of the main foundry facility, the replacement of two out-of-order converters with two new ones of a larger capacity with a system for the cooling of gases using the waste-heat boiler-utilizer and de-dusting in an electrostatic filter.
Also, the plan is for two new furnaces with an adequate system for gases to be built in the anode refinery, for a new water-cooled casting device to replace the current ones, the reconstruction of the area for the slow cooling of the slag and the construction of a new system for the filtering of converter waste gases.
As said, a new system for the removal of fugitive gases and a de-sulfuring device will be built, as will be a sulfuric acid plant, a waste water treatment facility and a new electrolysis facility. The preliminary design also envisages the construction of a new slag flotation facility, a lab and a new substation.
The most recent substantial reconstruction was carried out in 2015 by SNC Lavalin and Outotec. The reconstruction included the demolition of a furnace, the installation of a new flash smelting furnace (FSF), the construction of a new system steam drying system, waste-heat boiler-utilizer (WHB) and an electrostatic filter (ESP), as well as the construction of a new sulfuric acid plant.
As said in the document, a facility for the slow cooling of slag was installed within this reconstruction and a system for the preparation of batches was reconstructed. Also, the slag flotation facility and the Pierce-Smith (PS) converter gas treatment system were reconstructed as well. A new facility for the production of oxygen by Messer, a supplier of technical gases, was built. The anode and electrolytic refinery were kept during the reconstruction.
The preliminary design was prepared by the Faculty of Technology and Metallurgy in Belgrade and it is published on the official website of the City of Bor.
I. M.
Companies:
Serbia Zijin Copper doo Bor
Grad Bor
Tehnološko metalurški fakultet Beograd
SNC-Lavalin Montréal, QC Canada
Messer Tehnogas ad Beograd
Tags:
Serbia Zijin Bor Copper doo
SNC Lavalin
Outotec
RTB Bor
Messer
City of Bor
Faculty of Technology and Metallurgy in Belgrade
foundry
copper processing
electrolysis
sulfuric acid plant
cathode copper production capacity
copper concentrate transport
production of cathode copper
raw materials preparation system
smelting system
electrolysis system
system of production of acid from waste gases
slag flotation
service systems
facility for preparation of batches
steam drying system
reconstruction of main foundry facility
replacement of two existing converters
gas cooling system
anode refinery
construction of a furnace
water cooled casting device
reconstruction of area for slow cooling of slag
construction of new system for filtering converter waste gases
fugitive gas removal system
desulfuring device
waste water treatment facility
electrolysis facility
slag flotation facility
construction of new substation
Comments
Your comment
Most Important News
Full information is available only to commercial users-subscribers and it is necessary to log in.
Follow the news, tenders, grants, legal regulations and reports on our portal.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno,
uz konsultacije sa našim ekspertima.