Hyundai and UGT Renewables to Build State Solar Power Plants of Large Capacities – Strategic Partners Selected for Raising of at Least Five Facilities of 1 GW in Total
Source: eKapija
Tuesday, 31.10.2023.
15:08
Comments
Illustration (Photo: Unsplash/Andreas Gücklhorn)
This is the previously announced project of construction without management and maintenance of self-balancing solar power plants of large capacities with battery systems for the storage of electrical energy in Serbia. The future power plants will have a total installed power of 1 GW, and the plan is for the construction of solar power plants to be completed by June 1, 2028.
As said in the invitation, the project will be developed, built and handed over to the ownership of EPS as a turnkey project. That means that the strategic partners, in addition to building the solar power plants and battery system, will be obliged to build all the other infrastructure as well.
The project consists of two components: solar power plants and battery systems for the storage of electrical energy.
The solar power plants will have a total installed power of 1,000 MWac (that is, 1,200 MWdc), and in order to secure the optimal evenness of the production of electrical energy, the total installed power has to be distributed across five or more independent solar power plants.
The locations in which the solar power plants will be located, as well as the number and the installed power of each individual solar power plant, will be proposed by the strategic partner.
The battery systems for the storage of electrical energy, with a total installed power of at least 200 MW and a capacity of the accumulation of at least 400 MWh of electrical energy, will be distributed across several strategically important locations within the electrical energy system of Serbia.
Read more:
- The state is looking for a strategic partner for the construction of large-capacity solar power plants - An invitation issued for the construction of at least 5 plants with a total capacity of 1 GW
- Public Invitation for Strategic Partner for Construction of Solar Power Plants of 1 GW
- Details of Selection of Strategic Partner for Construction of State Solar Power Plants of High Capacity Announced – Facilities Need to Be Built by 2028
The locations in which the battery systems for the storage of electrical energy will be located will also be proposed by the strategic partner.
The Agreement on Cooperation between the US company UGT Renewables LLC, which is in the business of renewable energy sources, and the Ministry of Mining and Energy of Serbia was signed back in August 2021. The intention of this Florida-based company, as said at the time, was to build solar panels of a total power of around 1,000 MW, on an area of around 2,000 hectares, in around ten locations throughout Serbia.
Nova.rs wrote that this Miami-based company was also in the running for the strategic partner for EPS.
I. Z.
Companies:
Hyundai Engineering Co Ltd (HEC)
Vlada Republike Srbije
Elektroprivreda Srbije ad Beograd
Tags:
Hyundai Engineering Co LTD
Hyundai Eng America Inc
UGT Renewables LLC
Government of Serbia
EPS
selection of the strategic partner for the realization of the project of construction of self-balancing solar power plants of large capacities
battery systems for the storage of electrical energy in Serbia
construction of state solar power plants
strategic partner for the construction of solar power plants
solar power plants of large capacities
Law on the Use of Renewable Energy Sources
battery systems
Comments
Your comment
Most Important News
Full information is available only to commercial users-subscribers and it is necessary to log in.
Follow the news, tenders, grants, legal regulations and reports on our portal.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno,
uz konsultacije sa našim ekspertima.